Construction crews plan to close access from northbound US 31 to State Road 32 and from State Road 32 to northbound US 31 beginning on or after May 6. During the closures, contractors will connect pavement for the new northbound ramps at the single-point urban interchange being built as part of The New US 31 Hamilton County freeway.

Crews anticipate opening the northbound US 31 exit ramp to State Road 32 before Memorial Day (May 25), followed by the State Road 32 entrance ramp to northbound US 31 about one week later. This schedule is subject to change, pending unforeseen circumstances, such as inclement weather.

Both the southbound access from US 31 to State Road 32 and the State Road 32 access to southbound US 31 will remain open.

Detour for northbound US 31 access to State Road 32:

Motorists traveling northbound on US 31 must continue north to the interchange at State Road 38, exit and reenter US 31 going southbound and take the southbound US 31 exit to State Road 32.

Detour for State Road 32 access to northbound US 31:

Motorists traveling in either direction of State Road 32 must enter southbound US 31, exit to the 161st Street roundabout interchange and reenter northbound US 31.